2006 ISOE Asian ALARA Symposium
Niigata Prefecture with the involvement of about 40 participants from Japanese electric utilities and manufacturers,
and from the U.S. and Korea.
Led by Mr. Mizumachi, the chair-elect of the Steering Group, the introduction of the current situation of EPRI Standard Radiation
Monitoring Program and the report of the situation regarding occupational dose at Japanese nuclear power stations
are presented. Then, the technologies for dose reduction were introduced by Japanese manufacturers.
Moreover, efforts for dose reduction were reported by Japanese and Korean utilities, and they ardently exchanged discussion.
“ALARA Activities at Ohi NPP”, which was presented by Mr. Akira Nakamura of Kansai Electric Co., Inc, was
recognized as the best presentation and he was invited to ISOE International ALARA symposium 2007 that is planed
to be held in Fort Lauderdale in the U.S in January, 2007.
On the following day (13th), they visited Kashiwazaki Kariwa nuclear power station of Tokyo Electric Power Co.,
and observed unit 6, ABWR.
Title | Speaker | Contents | |
Summary Report of the EPRI Standard Radiation Monitoring Program |
Dr.Dennis Hussey EPRI |
Summary | Presentation Paper |
Occupational Exposure at Japanese Nuclear Power Plants in FY2005 |
Shigeyuki Wada JNES |
Summary | Presentation |
Introduction of dose reduction technology
Title | Speaker | Contents | |
Our Decontamination technologies for NPSs |
Tadasu Yotsuyanagi Toshiba Corporation |
Summary | Presentation Paper |
Approach of Hitachi for Dose Rate Reduction |
Nobuyuki Ota Hitachi, Ltd. |
Summary | Presentation Paper |
Introduction of the Decontamination Method Which Uses Blasting |
Toshiaki Ninomiya, Mitsubishi Heavy Industries, Ltd. |
Summary | Presentation Paper |
The current challenges and good practices of utilities
Title | Speaker | Contents | |
ALARA Programs & Occupational Dose Trend in Wolsong Nuclear Power Plant |
Choi Ki Young KHNP |
Summary | Presentation Paper |
Progress of the Zinc Injection in Tsuruga NPP Unit 2 |
Nobuaki Nagata Japan Atomic Power Company |
Summary | Presentation Paper |
Measures for containing an increase in pipes’ dose-equivalent rate in the hydrogen-injected environment at the Shimane Nuclear Power Station Unit 1 |
Hiroyasu Kajitani Chugoku Electric Power Co., Inc. |
Summary | Presentation Paper |
ONAGAWA NPS Dose Reduction |
Katsushi Wada Tohoku Electric Power Co.,Inc. |
Summary | Presentation |
ALARA Activities at Ohi NPP | Akira Nakamura Kansai Electric Power Co.,Inc. |
Summary | Presentation Paper |
Improvement of TEPCO’s ALARA process |
Shiro Takahira Tokyo Electric Power Company |
Summary | Presentation Paper |